After a rolling upgrade, some steps must be completed.

Verify all VMs are healthy

All the VMs in the deployment need to be healthy. To check this, run the common health checks for the VMs by following: Verify the state of the nodes and processes. The per-node checks should also be run by following each page under: Per-node checks.

Enable scheduled Rhino restarts

If you have disabled the scheduled Rhino restarts before the upgrades, then it can now be enabled. This can be done by uncommenting out the scheduled-rhino-restarts section in the VM pool YAML config files. Then to update the VMs with the scheduled restarts, use rvtconfig upload-config.

Previous page Next page
Rhino VoLTE TAS VMs Version 4.0.0