This upgrade process supports upgrades where the service in use may initiate outbound CGIN dialogs. |
1 |
Set up the new cluster
Now you should have the "new" cluster configured, but
|
||||
---|---|---|---|---|---|
2 |
Start the new cluster
|
||||
3 |
Drain calls from the old cluster
At this point, all new dialogs will be directed to the new cluster only. The old cluster will only continue to process existing dialogs established before the draining process started.
Now the old cluster should be still connected to the CGIN backends, but completely idle — no traffic is being handled by the old cluster.
|
||||
4 |
Stop the old cluster
|
||||
5 |
Shut down the old cluster
|
||||
6 |
Schedule upgrade of old backends to the new version
(if needed) |