After a rolling upgrade, some steps must be completed.
Verify all VMs are healthy
All the VMs in the deployment need to be healthy. To check this, run the common health checks for the VMs by following: Verify the state of the nodes and processes.
Enable scheduled Rhino restarts
If you have disabled the scheduled Rhino restarts before the upgrades, then it can now be enabled.
This can be done by uncommenting out the scheduled-rhino-restarts
section in the VM pool YAML config files.
Then to update the VMs with the scheduled restarts, use rvtconfig upload-config
.